Question No 4:
As the maintenance manager for a manufacturing company, you have conducted a study that reveals the mechanics, on average, spend four hours per ten hour shift on wrench time (tool turning time). Your first action should be:
A. Improve planning and scheduling to increase wrench time (tool turning time).
B. Encourage your planners to develop more aggressive job estimates.
C. Inform management that four hours wrench time (tool turning time) per day is considered good.
D. Investigate the barriers causing loss of wrench time (tool turning time).
Answer: A